It’s no longer just plans or mock ups. It’s reality.
Caltrain is finishing electrification and testing electric trains through the summer 2024. Soft launch is planned to occur in early August and new schedules with all electric trains between San Francisco and San Jose is planned to start in late September. Diesel trains will continue to operate between Gilroy and San Jose.
What is electrification?
Caltrain currently runs on diesel. The electrification project would convert diesel propulsion to electric propulsion. Electricity would be delivered to the trains through overhead wires.
Why Electrify?
- Faster, electric trains accelerate and stop more quickly.
- More service. Faster acceleration would allow more station stops with the same amount of travel time, which would restore service to some stations that had been reduced since 2004. Shorter travel times also allow the same trains to run more trips throughout the day.
- Cleaner, because electric trains will not spew tons of harmful diesel pollutants.
- Quieter, because electric trains have no diesel engines revving up day and night.
- More reliable, electric train motors experience less down time than diesel engines.
- Reduce dependence on foreign oil, because electric trains can take advantage of cleaner domestic electricity. For a fraction of the cost, electrification would save 1.7 times as much fuel as building a BART train line from San Jose to Fremont.
What is EMU?
EMU stands for electric multiple units. Instead of having a single locomotive that pushes or pulls passenger cars. The passenger cars would have their own electric motors. In the Bay Area, Muni Metro, VTA light rail, and BART trains are all electric multiple units.
EMUs are more reliable and have the same performance no matter how short or long a train is. EMU trains can be configured so their lengths can be changed easily, which permit shorter trains during off-peak hours to reduce costs.
Electrification campaign history
In 1983, PR2000 released a series of white papers: “5-Point Program To Develop and Improve Peninsula Rail Service.” It includes electrification, along with Downtown SF extension and other proposals. Members handed out newsletters to train riders, made presentations to Peninsula city councils, SamTrans; appeared on local radio stations.
In 1992, PR2000 (later known as BayRail Alliance) successfully lobbied to include Caltrain electrification in Santa Clara County T2010 plan, and in the Measure A half-cent sales tax that was later struck down by the State Supreme Court. Caltrans and JPB electrification studies confirmed key part of 5-Point Plan. On two advisory ballot measures, PR2000 helped persuade more San Mateo County voters to support Caltrain than BART.
In 1999, newcomer Margaret Okuzumi helped PR2000 mount a pro-electrification faxed letter campaign. The JPB voted 5-to-4 at their May 6 meeting, to make electrification a near-term priority, instead of adopting the “go-slow” approach recommended by staff.
Video below is a 3D animation done in early 2000s to promote electrification to policy makers.
Environmental Clearance
After the Caltrain board first approved electrification as a priority in 1999, the agency began environmental evaluation in 2001. Because of funding issue, the final EIR was released in 2009 but the board chose not to certify it under the threat of litigation. The federal version of the environmental document was approved by the FTA in 2009.
The project was stalled for a few years while Caltrain and High Speed Rail Authority were trying to determine the future of the Peninsula Corridor with High Speed Rail. The High Speed Rail Authority initially planned for a completely grade separated 4 track corridor. Because of funding concerns and community rejection, Caltrain, the High Speed Rail Authority, regional transportation entities including MTC, and the state legislature agreed on a blended approach in 2012 for High Speed Rail which envisions the corridor to be primarily 2 tracks shared by Caltrain and High Speed trains. Electrification of Caltrain was included in the 2012 High Speed Rail business plan as part of early investment package and would be used by High Speed trains under the blended approach.
After the approval of the High Speed Rail plan by the state legislature in the summer of 2012, electrification officially became “fully funded” with funding from Proposition 1A. In 2014, Caltrain released a new draft environmental impact report for this project.
In July 2016, JPB voted to approve contracts for construction of electrification infrastructure and purchase of electric rolling stock. After months of unnecessary delays in 2017 due to change in administrations, the federal government formally approved a key grant for the project after intense lobbying by business groups as well as Senator Feinstein and Governor Brown. Electrification construction began in July 2017. After suffering delays caused by COVID-19 and a collision in San Bruno between a train and construction equipment in 2022, the construction reached “substantial completion” in May 2024, after many weekends of partial shutdown of the rail line in 2023 to catch up.
» Construction updates and meetings
FAQ
- If the diesel fuel cost is so high, shouldn't Caltrain be running shorter trains during off-peak hours to save fuel?
- Why is Caltrain electrification so important?
- How much travel time will be saved by electrifying Caltrain?
- Is electrification happening instead of extending the train to downtown San Francisco?
- Why not replace Caltrain with BART? Won't that cost the same as electrifying Caltrain?
- Why is Caltrain proposing to use EMUs instead of electric locomotives?
- Is Caltrain planning to electrify all the way to Gilroy? If not, then what will happen on the Gilroy segment?
- Why not use ground-level third rail?
- Won't it be unsafe to have high voltage lines all over the place?
- Won't the overhead wires be an ugly visual intrusion?
Green Caltrain updates on electrification
- Bill proposes CEQA exemption for rail electrification; spare other projects from delays that affected Caltrain
- Caltrain grapples with fiscal cliff, increased costs of running an electric system
- BART directors seek to explore expanding rail district, consolidations with Caltrain and other agencies
- This Saturday and in September – tour Caltrain electric trains!
- Caltrain passes 2-year budget with steady service, partner contributions – but risks lie beyond