BayRail general meeting

June 7, 2005

June 7, 2005 — BayRail Alliance, working with TRANSDEF, files a “friend of the court” (amicus) brief along with the Sierra Club, TRAC, San Francisco Tomorrow, and TALC, requesting speedy appeal of a ruling on the Transbay Terminal project’s Environmental Impact Report (EIR). A ruling by a judge in favor of private developer Jack Myers has halted preliminary planning and engineering for the project. The groups ask the appeals court to stay (halt) the judge’s order pending appeal. This succeeds in producing a speedy stay of the order, allowing planning and engineering for the Transbay Project to proceed. Myers later drops the appeal after the City of San Francisco agrees to pay $34 million to acquire his property through eminent domain.